POWER PLANTS PAKISTAN

Our first realization of contracts for Asia: COMBINED CYCLE POWER PLANTS PAKISTAN (2008 – 2009)

Supply, assembly and supervision and commissioning of gas equipment in power plants in Pakistan:

–        BALLOKI 225 CCPP – PAKISTAN

Inlet EDS valve, safety slam shuts, two filtration and metering lines for 56 000 m3/h flow, gas pre-heating for hot-water exchangers 800 kW, gas boiler-room 1,2 MW for gas pre-heating (container design), compressor station with three CAMERON compressors including pressurized air, nitrogen and cooling system networks. RS 1200/2/2-440 regulation station for boiler-room.

Technical parameters:
Qmax = 56 000 m3(s)/h
Inlet pressure: 25 – 45 bar
Outlet pressure: 23 – 28 bar
Outlet temperature: 30 °C

–        MURIDKE 234 CCPP – PAKISTAN

Inlet EDS valve, safety slam shuts, two filtration and metering lines for 56 000 m3/h flow, gas pre-heating with 800 kW warm water heat-exchangers, 1,2 MW gas boiler-room for gas pre-heating (container design). RS 1200/2/2-440 Gas regulation stations for boiler-room.

Technical parameters:
Qmax = 56 000 m3(s)/h
Inlet pressure: 28 – 40 bar
Outlet pressure: 28 bar
Outlet temperature: 30 °C

pakistan1               pakistan2